|

Providing
the supply of clean water
The
water in Skerries comes from the river Liffey via Leixlip. The
council fixes all bursts and leakages and carries out an on-going
programme of upgrading valves and other equipment that have outlived
their useful lives. Water is sampled on a continuous basis to
ensure it meets quality standards.

Looking
after our drains and sewerage - where does it all go?
All
sewerage in Skerries gravitates to a pumping house beside the
Rugby Club on the Rush Road. It is then pumped through a pipeline
to Shenick Island. On the island it collects into a large septic
tank for settlement to take place. It is then discharged into
the sea. This system will be discontinued when the new water treatment
plant is built. See below.
The
sewers in the town are maintained on a regular basis. Local inspectors
identify any problems and arrange for the sewers to be cleaned
and repaired. Last year new foul sewers were installed in Little
Strand Street and in other parts of the town centre. A new foul
sewer (1 km in length) was built from the pumping station by the
Rugby Club along the Rush Road as far as the reservoir.
The
surface water system in the town-centre was upgraded recently.
Formerly surface water had drained into the foul system putting
extra pressure on it. This is no longer the case. The surface
outfall to the South Strand was upgraded as a flood protection
measure.
Other
flood relief works were also carried on the Brook from the entrance
to Skerries Mills down as far as the beach. These works included
clearing out all the weeds from the Brook along this stretch.
Remedial works were carried out on surface water lines into the
Brook from Millers Lane.
Contact:
PJ Howell, Director of Water Services, 890 5000

Balbriggan/Skerries
DBO Waste Water Treatment Scheme Project Update No. 2 –
March 2005
Treatment
Works Site - Barnageeragh
The site at Barnageeragh, Skerries will house the various tanks/components
necessary to treat the incoming waste water. To date, all of the
site clearance has been completed, this work included removal
of topsoil, old hedges, etc.
The
excavated topsoil will be used in the final landscaping. During
the site clearance activities, an area of archaeological interest
was uncovered at the southwest corner of the site. A full dig
was commissioned to ascertain the nature of the prehistoric find;
the main areas of interest were numerous burn marks and pits and
evidence of a circular ditch, The final report on this dig is
pending.
The
palisade fencing, which will form the permanent boundary to the
site, is approximately 80% complete. Staff accommodation is also
complete. This includes offices for the Resident Engineering staff
and Contractors Engineering staff, storage cabins, canteen and
welfare facilities for the operatives and an external storage
area.
Landscaping is also well underway. The Environmental Impact Statement
States that a berm, varying in height between 3.5 - 6.0m must
be built around the site boundary to limit the visual impact of
the finished works. Material excavated from Quay Street, Balbriggan,
is being utilised to construct a portion of the berm. Part of
the landscaping work included the diversion of a stream, running
through the middle of the site, this stream now runs along the
inside of the north site boundary.
Quay
Street Storm Water Tank-
Quay Street car park in Balbriggen was closed to the public on
January 24th, 2005. Signs were placed around the car park and
in the train station prior to the closure to warn commuters and
car park users of the closure. A letter drop was also undertaken
in the vicinity of Quay Street. The entire car park has been fenced
off to prevent any access by members of the public. The pedestrian
entrance to the train Station may still be accessed via the harbour
road or through the 2nd car park adjacent to Quay Street.
The
clothing bank located in the car park had to be removed in order
to facilitate the works, signs are in place on the fencing directing
people to an alternative clothing bank location.
The
Temporary Works commenced on the 3rd of February. This consists
of an interlocking sheet pile system, driven into the ground to
rock level. A steel bracing system was welded around the inside
of the sheet piles just below existing ground level. The objective
of these temporary works is to retain the surrounding soil and
to provide a safe working area. On completion of this part of
the bracing system excavation for the tank commenced, with excavated
material transported to Barnageeragh in HGV’s. Additional
bracing will be required when the bottom of the sheet piles are
excavated. Any water encountered in the excavation is pumped into
the adjacent stream, which flows into the harbour. Prior to discharge,
the water passes through a settlement tank to eliminate sand and
grit etc.
On
completion of the storm tank, the car park will be fully reinstated
and opened to the public.
Contact:
John Mulcahy, Swords Project Office 890 3100

Keeping
Our Streets Clean
The
following is the street cleaning schedule:
 |
Thomas
Hand St. |
 |
Dublin
Rd., |
 |
The
Square |
 |
Balbriggan
Rd |
 |
Church
St. |
 |
Strand
St. |
 |
Main
St. |
 |
Chapel
Lane |
 |
New
St. |
 |
All
laneways leading to Strand Street. |
The
areas above are picked of litter and swept with the green machine
from Monday to Friday between 08.00 and 16.30. At weekends (Sat
& Sun) the litter is picked in those areas between 07.00 and
11.00 am. The streets in the Hoar Rock area are cleaned when required.
All
litterbins are attended to every day (seven days) and the mechanical
sweeper sweeps the main areas in Skerries every Saturday.
Eamonn
Harford and Stephen Carey are the Street Cleaners, Don Costigan
is the Supervisor and Niall Gargan is the Inspector and can be
contacted on 8905956/57

Traffic
Management Scheme
The
traffic plan is going ahead on the basis of the decision of the
Council last autumn. Surveys are taking place at the moment, which
will lead to detailed drawings for exactly where parking spots
are to be etc. These should be available in early July. They will
then go to tender and contract, and are expecting work to start
in October. There will be an opportunity during the summer for
detailed tweaking, but the structure of the plan will not be changed.
They intend to start with the town centre.
Contact:
Peter Caulfield, Transportation peter.caulfied@fingalcoco.ie
BACK
TO FINGAL COUNTY COUNCIL INDEX PAGE
|